Hey Gang! How are things? Great to hear. Oh I am fine. Could use a haircut though… But enough about me – how about some more info on the new CJSW Broadcast Centre and the annual Funding Drive campaign?
The CJSW Broadcast Centre is nearing completion. Since the last posting, the Phase Two (construction of the new offices for staff and volunteers) has transformed from a skeletal steel shell to a space that is actually looking like a radio station with drywall and paint.


A view from the curved volunteer meeting area. If the bin looks familiar, it is because it was used in one of the Indiana Jones films. Or was it one of the Police Academy films? Part three or part eight? Oh I can’t remember…

Stilts! Without a safety net! Brilliant!


Future news department area. Quilted jacket not included.


Work on the future home of CJSW’s library is also nearing completion, with the final touches on lighting and the ceiling now underway. We will be bringing up the vinyl shelves from our current space up to the new one but new CD shelves will be installed over the next few weeks.

Entrance to the bigger and better CJSW library.

Shelves will wrap around the outside of this room with several “CD islands” built in the middle for programmers to access our musical collection.

It is hard to get excited about a floor drain but when you have been flooded as many times as CJSW has, this is one of the greatest things you will see. If we do get flooded, which should be more unlikely and preventable than before, this drain will help save the day. In fact, the new library shelves will be built with mini-roofs to deflect any precipitation that may wish to visit us from the basement.
What is next you ask? This past weekend, the entire exposed concrete floor of the space was sealed. Finishing touches on electrical and mechanical will take place this week. Mike the Engineer and his crew are still frantically pulling wire to get the studios ready to go on-air. The sound spaghetti is pulled from here:

To here:

Here is a shot of some outlets waiting for “ON-AIR” signs to be stuck to them. Well not stuck-stuck, but bolted and such.

We are aiming to test all of the “systems” in early November and move in shortly after that. Dare I say all will be good to go by mid-November? Stay tuned…
Lastly, Happy Funding Drive. We are about 1/3 of the way through and things are going very well. I want to quickly thank everyone who has supported us so far and all of the CJSW volunteers for their hard work. The tally so far, as of Monday morning, is $75,000. We hope you can support us as we prepare to finish up this grand project and continue to bring you fantastic campus and community radio. If you need more info about the CJSW Funding Drive, please check out www.cjsw.com/funding.html and pledge today.